Pratt Parkway Bridge
Zak Dirt, Inc. is working on a bridge replacement, minor channel rehabilitation, a bike path and retaining walls.
Location: Longmont, CO |
see below to scroll through photos & enlarge
|
Project Updates:
Fluctuating river levels has prolonged landscape next to the river by two weeks. Much of the site has been seeded and blanketed, and more than a hundred thousand wetland plants planted. Landscaping work will continue until July 4th, at which time we should be ready to apply for substantial completion.
Updated By: admin
Phase 1 substructure has been completed on the Pratt Parkway Bridge and crews are finishing grading and riprap before erecting 18 concrete box girders weighing 90,000 lbs. each. Crews also successfully installed a 12’ diameter water-treatment manhole in a 20’ deep excavation only feet away from a building, a waterline, and live traffic.
Updated By: admin
Phase 1 abutment columns and pier walls are complete. False work and forming of pier caps is underway. Also underway is construction of the block retaining wall. Upcoming work includes installation of a 12” waterline across Saint Vrain Creek and new storm drain pipe south of the bridge.
Updated By: admin
A soil-nail shoring wall is currently being constructed along the project phaseline to allow for the new longer bridge by preventing collapse of the roadway. We are also drilling fifteen caissons for the substructure of the west half of the bridge. The girder plant has begun to cast the phase 1 concrete box girders, and the retaining wall block supplier has begun to cast blocks for our design-build geogrid-reinforced retaining wall at the south abutment.
Updated By: admin
Phase 1 traffic switch and phase 1 bridge demolition is complete. We are working to install shoring and caissons.
Updated By: admin
As always, weather or encountering unknown conditions may cause unforeseen delays to the construction schedule. Every effort will be made to inform you and keep you apprised of changes.
-
Click to enlarge Pratt Parkway Bridge
6/20/2018
-
Click to enlarge Completed pier wall; pier cap to be built on top to complete the bridge substructure
6/19/2018
-
Click to enlarge 12’ manhole riser
6/19/2018
-
Click to enlarge Retaining wall with storm drain penetration; bridge abutment tied and formed above
6/19/2018
-
Click to enlarge Caisson drilling at Pratt Parkway Bridge
2/27/2018
-
Click to enlarge West bridge demolition
2/25/2018