Button Rock Dam Road Culvert Replacement

The existing 80” culvert failed and was replaced with a 20’ x 10’ concrete box culvert. A boulder drop structure was placed both upstream and downstream of the new CBC to facilitate the 8’ of grade drop. This project is a State of Colorado 2012 APWA award recipient for Design/Construction/Maintenance.

Location: Longmont, CO
Owner: City of Longmont
Contract Amount: $350,000.00
Start Date: 12/31/2011
Completion Date: 4/19/2012






see below to scroll through photos & enlarge
 
 
  • Click to enlarge

    Pre Construction – Downstream Existing Culvert
    4/26/2012

  • Click to enlarge

    Button Rock Dam Road Culvert Replacement
    4/26/2012

  • Click to enlarge

    Completed Box culvert – Upstream Box culvert and drop structure
    4/26/2012

  • Click to enlarge

    Completed Box Culvert – Downstream Box Culvert and Drop Structure
    4/26/2012

  • Click to enlarge

    Completed Box Culvert and Drop Structure Downstream. Installation of Handrail
    4/26/2012

  • Click to enlarge

    During Construction – Upstream Wing walls and Drop structure
    4/26/2012

  • Click to enlarge

    During Construction – Downstream Drop Structure
    4/26/2012

  • Click to enlarge

    Pre Construction – Upstream Existing Culvert
    4/26/2012

  • Click to enlarge

    Pre Construction – Downstream Existing Culvert
    4/26/2012

  • Click to enlarge

    Button Rock Dam Road Culvert Replacement
    4/26/2012